How one license sets the river's floor

The Spokane River Project is licensed by the Federal Energy Regulatory Commission (FERC, the agency that permits most non-federal hydropower) under a single project number, P-2545. Avista received a new license for it in 2009, with a term of about 50 years, which runs toward roughly 2059 at last public report. The license bundles several developments on the river, including Post Falls just over the Idaho line, Monroe Street in downtown Spokane, Nine Mile, and Long Lake.

What makes the license matter to a ratepayer is the flow rules. It sets minimum flows (the least amount of water that must pass a given point) for aquatic life and, well known locally, for the Spokane Falls themselves, so the falls keep running during daytime hours in the visitor season rather than being drawn down to squeeze out more power. When the river is low, those floors can cap how much Avista is allowed to generate. The water comes first, the kilowatt-hours second.

The honest math on an old urban fleet

Add up the Spokane River developments and you get a modest number by Columbia standards, on the order of 150 megawatts of capacity across the chain, per Avista's project descriptions. A megawatt is roughly enough to serve several hundred homes at a given moment, so this is real power for the region, not a rounding error, but it is a fraction of what a single large Columbia dam puts out.

Output is not steady, either. Spokane River flow swings with the snowpack in the mountains of north Idaho and eastern Washington, high in the spring melt and low by late summer. The honest version: in a dry late summer, with flow floors to honor and little water to spare, these dams make far less than their nameplate suggests. The license, not the turbines, is often the binding limit.

Who holds the pieces

Avista owns and runs the dams, but it does not set the rules alone. FERC issues and enforces the license. Washington's Department of Ecology issued the water quality certification (a state sign-off, under the federal Clean Water Act, that the project will meet state water standards) that is folded into the license. The Washington Department of Fish and Wildlife and tribal governments, including the Spokane Tribe and the Coeur d'Alene Tribe, hold long-standing interests in the river's fish and flows.

For a reader, this means the accountability is public and checkable. The license and its compliance filings sit in FERC's eLibrary. Avista's own project pages describe the flow commitments. If you want to know whether the falls should be running on a July afternoon, the answer is written in a document you can pull up, not left to the utility's discretion.

Worth watching this month

1. Watch the winter snowpack reports for the Spokane River basin from federal water agencies, since a thin snowpack now tends to mean tighter summer flows and lower hydro output later; this is routine but it sets the year.

2. Check the USGS streamflow gages on the Spokane River for current readings, which tell you roughly how much room the dams have above their license flow floors.

3. Look for any Avista filings in FERC's eLibrary under project P-2545, where compliance reports and any proposed license changes would show up; most are routine paperwork, a few actually matter.

4. Watch Washington Department of Ecology notices for anything touching the project's water quality certification, uncommon in a given month but worth noting when it moves.

5. Follow Avista's rate activity at the Washington Utilities and Transportation Commission, since what these dams cost to run eventually reaches your monthly bill.

Questions from readers

Does Avista own the whole Spokane River?

No. Avista owns a chain of hydroelectric dams on the river under one federal license, but the river itself is a public waterway shared across Washington and Idaho. State agencies and tribes hold legal interests in its flow and its fish.

Why do the Spokane Falls run even when the utility could use that water for power?

The project's FERC license requires minimum flows over the falls during certain hours and seasons, so the falls keep running for the look of them and for recreation. Those rules can limit how much Avista generates at the time.

When does the current license expire?

Avista received a new license in 2009 with a term of about 50 years, so it runs toward roughly 2059 at last public report. Check FERC's record under project P-2545 for the exact dates.

How much power do these dams make?

On the order of 150 megawatts of capacity across the chain, per Avista's descriptions. Actual output rises and falls with river flow and is often far lower in a dry late summer.

Where can I check the river flow myself?

Federal streamflow gages on the Spokane River post near real-time readings online. The project license, public in FERC's eLibrary, spells out the minimum flows the dams must leave in the river.

Sources for this story

  1. FERC eLibrary (federal regulator), Search project number P-2545 for the Spokane River Project license and Avista's compliance filings., elibrary.ferc.gov/eLibrary/search
  2. Avista, hydro generation (utility), The utility's own description of its Spokane River dams and the flow commitments in the license., www.myavista.com
  3. Washington Department of Ecology (state agency), State water quality certification and water standards that are folded into the federal license., ecology.wa.gov
  4. USGS Water Data (federal agency), Near real-time streamflow gages for the Spokane River so you can read current flow yourself., waterdata.usgs.gov
  5. Washington Department of Fish and Wildlife (state agency), State interests in the river's fish and habitat that shape the project's flow and aquatic rules., wdfw.wa.gov
  6. Washington Utilities and Transportation Commission (state regulator), Where Avista's rate cases are filed and reviewed, connecting the dams' costs to your bill., www.utc.wa.gov