What the plant actually makes
Polysilicon starts as ordinary metallurgical silicon and gets purified until it is almost entirely silicon, clean enough for electronics and solar cells. REC Silicon makes it with a fluidized bed reactor (a method that grows silicon as small granules inside a heated column of gas) rather than the older rod-shaped Siemens process. The gas that feeds that reactor is silane, which the company also sells on its own.
That silane is where the plant's two futures split. Solar-grade polysilicon goes into panels, while semiconductor-grade and the newer battery-grade silane can feed silicon battery anodes, a market the company has said it wants to serve. The same Moses Lake chemistry points at two very different customer lists, and each list qualifies material on its own terms, which turns out to matter a great deal.
The power it runs on
Making polysilicon is the single most power-hungry step in a panel's life, which is why these plants follow cheap electricity rather than the other way around. At full operation the Moses Lake plant drew on the order of a few hundred megawatts, per the company's past disclosures, making it one of the largest single loads in Grant County. That power comes from Grant County PUD, the public utility district that runs the Priest Rapids and Wanapum dams on the Columbia River.
Hydropower rates in the Columbia Basin are among the lowest in the country, which is the whole reason the plant sits here and not somewhere else. Bonneville Power Administration, the federal agency that markets most of the region's dam output, sets the wider price and reliability backdrop. All of it runs under the state's Clean Energy Transformation Act and its 2045 deadline for carbon-free electricity, so a plant on hydro is, on paper, a clean-energy supply chain running on clean power.
Running, idled, or winding down
Here is the honest status, and it is not a clean yes or no. The plant idled its polysilicon production around 2019, after China's tariffs effectively closed off its main export market. Hanwha, the Korean parent of solar maker Qcells, later took a large stake, and FBR polysilicon production restarted around 2023 and 2024 with a domestic solar supply chain in view.
Then came qualification trouble. At last public report, in 2025, the main customer had raised concerns that the material was not meeting agreed specifications, and REC Silicon moved to stop FBR polysilicon at Moses Lake. Whether that proves to be a pause, a sale, or a permanent close is the open question, and the only reliable answers sit in the company's own filings and announcements and in Grant County PUD's public record, not in anyone's forecast.
Worth watching this month
1. Watch REC Silicon's quarterly investor updates for any disclosure of a Moses Lake restart, sale, or confirmed closure, which is the figure that actually matters here.
2. Watch Grant County PUD board agendas and minutes for any change to the plant's large-load power contract, usually routine but occasionally telling.
3. Watch Qcells and Hanwha supply-chain announcements for whether a domestic polysilicon source is still part of their stated plan.
4. Watch the U.S. Treasury's guidance on the 45X advanced manufacturing tax credit, which shapes whether American-made polysilicon can pencil out at all.
5. Watch the EIA's Washington electricity data for a drop or rebound in large industrial load, a slow and routine signal rather than breaking news.
Questions from readers
Is the Moses Lake plant open right now?
At last public report the company had moved to stop its FBR polysilicon production there, so it may be idled or winding down. The most current status is in REC Silicon's own announcements, which is where to check before assuming either way.
Why make polysilicon in Washington at all?
Polysilicon is the most electricity-intensive step in a solar panel, so it chases cheap, steady power. Columbia Basin hydropower, sold by Grant County PUD, is among the cheapest in the country, which is the main reason the plant is here.
What is the difference between solar-grade and battery-grade silane?
Solar-grade material feeds polysilicon for panels, while battery-grade silane can go into silicon anodes for batteries. They serve different customers and are qualified to different technical standards, so passing one does not mean passing the other.
Does the plant's power count as clean under state law?
Columbia River hydropower is carbon-free, so it fits the Clean Energy Transformation Act's goal of carbon-free electricity by 2045. Large hydro's tradeoffs, especially for salmon, are a separate and ongoing debate in this state.
Sources for this story
- REC Silicon company announcements and investor updates, The company's own filings on production status, customer qualification, and the Moses Lake plant; the primary source for whether the plant is running., www.recsilicon.com
- Grant County PUD, The public utility district that owns Priest Rapids and Wanapum dams and supplies the plant's power; board agendas and rate records are public here., www.grantpud.org
- Bonneville Power Administration (bpa.gov), Federal power marketer for most Columbia and Snake River hydro; context on regional power prices and reliability., www.bpa.gov
- U.S. Energy Information Administration, Washington profile (eia.gov), Federal data on Washington's electricity mix and industrial load, useful for tracking large demand shifts., www.eia.gov/state/?sid=WA
- Washington State Department of Commerce, Clean Energy Transformation Act (commerce.wa.gov), State agency page explaining the 2045 carbon-free electricity law that frames the plant's clean-power claim., www.commerce.wa.gov/growing-the-economy/energy/ceta
- Qcells (Hanwha) U.S. operations, The solar maker tied to REC Silicon through Hanwha; its supply-chain statements signal demand for domestic polysilicon., www.qcells.com/us