What the plug at the pier actually does
Cold ironing is the older name for it, from the era when ships burned coal and the iron engines went cold at the dock. The modern version lets a vessel switch off its auxiliary diesels, the engines separate from propulsion that run the hotel load: lighting, heating, refrigeration, pumps. At berth those auxiliaries can idle for roughly 8 to 12 hours on a cruise call, and longer when a container ship is working cargo.
Dock-side gear is substantial: a high-voltage connection, sometimes a frequency converter (many foreign hulls run on a different electrical cycle than the local grid), and cabling long enough to reach each ship's hookup. Not every vessel is wired to receive it, and not every berth is energized. That mismatch is the whole practical story, and the reason diesel at the pier has not simply vanished.
How many megawatts a hull pulls
A large cruise ship's hotel load at berth is on the order of several megawatts, commonly cited at roughly 7 to 11 megawatts for the biggest vessels, depending on size and weather. A container ship working cargo tends to pull less, often in the low single-digit megawatts, though it may sit at the pier longer. For a rough sense of scale, one big cruise ship on shore power can draw about as much as a few thousand homes for the hours it is plugged in.
It is real load for a city utility to plan around, but it is concentrated and predictable: a handful of berths, a published cruise schedule, mostly in the stretch from about April through October. Seattle City Light and Tacoma Power can see it coming, which is a different problem than a sudden heat wave. The honest uncertainty sits on the ship side, in how many calling vessels are actually equipped to plug in on any given day.
Who carries the load, and what it displaces
Seattle City Light serves the Port of Seattle's cruise terminals at Pier 66 on the downtown waterfront and Terminal 91 at Smith Cove, both of which have shore power installed, per the port's project pages. The utility runs mostly on hydropower, from its Skagit River and Boundary dams, and reports being carbon neutral. Tacoma Power, part of Tacoma Public Utilities, serves the Tacoma side of the Northwest Seaport Alliance and is likewise largely hydro.
The diesel displaced is marine fuel burned right at the waterfront, in and around neighborhoods like Interbay and the Duwamish Valley, where port emissions have long been an environmental justice concern. Swapping that fuel for Columbia and Skagit hydro is the point: cleaner air at the pier, and load that mostly fits Washington's Clean Energy Transformation Act, the 2019 law putting the state's electricity on a path to 100 percent clean by 2045.
Worth watching this season
1. The Northwest Seaport Alliance's shore power build-out at its container terminals, where added berths are slated to be energized over time; watch the Alliance's project updates for which ones actually go live, as this is where the next real load lands.
2. The Port of Seattle's 2026 cruise season dates, roughly April through October, which set when the heaviest shore power demand shows up and which is routine rather than a surprise.
3. Any Seattle City Light resource or rate filings at the Washington Utilities and Transportation Commission, where new port load would appear if it starts to matter for planning.
4. Washington Department of Ecology or U.S. EPA action on marine and port air emissions, which is what pushes ships and berths to get wired faster.
5. Tacoma Power's load and rate updates, since the Tacoma side of the Alliance is earlier in its shore power path than Seattle's cruise terminals.
Questions from readers
Will shore power lower my electric bill?
Not directly. The port and the shipping lines pay for the electricity the ships draw, so the benefit to you is cleaner waterfront air and better use of existing hydro, not a lower rate. Any rate effect would come slowly through long-run utility planning, not a new line on your statement.
Does every ship have to plug in?
No. Requirements are rolling out gradually, and a ship can only use shore power if both the vessel and the berth are equipped for it. Many calling ships still are not wired for it, so diesel use at berth has not disappeared.
Where does the electricity come from?
Mostly hydropower. Seattle City Light and Tacoma Power both run largely on hydro from the Columbia, Skagit, and other river systems, so the power at the plug is close to carbon free.
How much power does a single ship use at berth?
A large cruise ship draws on the order of several megawatts, commonly cited at roughly 7 to 11 megawatts; container ships generally pull less. Those are rough figures that vary with ship size, duration, and weather.
Sources for this story
- Seattle City Light (government utility), The public utility serving Seattle's port terminals; see its hydro resource mix and carbon-neutral reporting., www.seattle.gov/city-light
- Washington State Department of Ecology (state agency), State agency tracking marine and port air emissions and the role of shore power in cutting them., ecology.wa.gov
- U.S. EPA Ports Initiative (federal agency), Federal background on shore power, also called onshore power supply, and on port-related diesel emissions., www.epa.gov/ports-initiative
- Bonneville Power Administration (federal power marketer), The federal marketer behind much of the Northwest hydro that ultimately feeds these utilities., www.bpa.gov
- Port of Seattle shore power, Project pages for shore power at Pier 66 and Terminal 91 cruise berths., www.portseattle.org
- Northwest Seaport Alliance, The Seattle and Tacoma marine cargo partnership's terminal electrification updates., www.nwseaportalliance.com